The first post is always the hardest to write, and this
has been no exception. This entry was
written over a year ago, and has been changed many times - partly because the
technology has advanced over that time, but partly because my opinion has
changed too. So here it is, my first
formal blog post, enjoy!
Early in the learning curve, most contractors are told not
to add water to a load of pervious concrete.
The fear is that the concrete will become too wet, and not end up truly
pervious.
Relax. It's okay to
add water on the jobsite. Without
enough water, the cement will be starved, and the concrete won't develop the
strength it needs to hold traffic. So,
if the mix is too dry, add water. To
quote the NRMCA's text reference for their Pervious Concrete Contractor
Certification, "Adjustments can be made to a load that is too dry by simply
adding a little water."
Now that I've told you it's okay to add water, understand it
must be done carefully so that the mix doesn't become too wet. To understand this better, there are three
possible problems with adding too much water: the paste can become too thick
and close the voids, the paste can become too slick and allow the concrete to
compact too easily, or the paste can become too loose and bleed down through
the pavement causing it to seal below the surface. Understand these, and you'll have a better feel for how much
water you can add on the jobsite.
First, let's look at paste thickness. Paste in this situation is made of portland
cement, water, and any other powder like fly ash or slag. A typical pervious concrete mix is designed
with about 20% paste and 20% voids.
They say that below 15% voids, the concrete isn't truly pervious. In a typical mix, then, you have about 5%
extra voids as a safety factor. As you
add water to a pervious concrete mix, the ratios change - paste content goes
up, and voids go down. Going through the
math, you'd have to add about 10 gallons per yard to add 5% paste, and lose 5%
voids. I'm not saying go ahead and add
80 gallons to a load, because the next two issues might pop up at lower water
contents.
Next, let's look at compaction. The voids in a pervious concrete mix are designed using the
standard compaction of the Dry Rodded Unit Weight. If the aggregates are lubricated with cement paste, then those
voids might close more easily through compaction. The wetter a mix is, the slicker the paste will be, and it will
be easier to reduce that void space.
Adding water to a mix that has no sheen won't impact this, but adding
water to concrete that already has sheen and is compacting easily could lead to
trouble. Unless you are using very
heavy compaction equipment, though you won't be likely to see this - more often
you'll see one of the other two issues pop up first.
Lastly, we need to talk about paste bleed. This happens when the paste is too wet and
seeps down through the voids. You won't
notice this at the surface unless you watch carefully as the concrete sits, to
see the paste oozing down off the aggregate.
From my experience, this happens when three to four gallons of water is
added to a good load of fresh concrete.
If a viscosity modifying admixture is in the concrete it
will probably be able to take an extra gallon or two per yard without bleeding,
giving you more freedom to add water without worrying.
As always, before the job starts, the contractor and
producer need to test the proposed mix to determine its range of water
sensitivity, and come to an agreement as to how much water can safely be added
to a load. Until we have a standardized
procedure for testing the water sensitivity of a load of pervious concrete,
here are a few rules of thumb to try in the field (assuming the mix has 600
pounds of cement per yard):
- If the
concrete has no sheen, add three to four gallons of water per yard to the
truck before it leaves the batch plant and check it again.
- If the
load had sheen, but is drying up, add two to three gallons per yard
- If the
load has good sheen and is compacting well, leave it alone
- If the
load takes more than five gallons per yard, it was probably batched too
dry (We'll talk about this more in a later post.)
In the end, don't be afraid to add water to a load of
pervious concrete that truly needs it.